Structure - Granite Manor Spark Structure in primary. This structure is built for kids ages 2-5 and includes a double bed slide, a single wave slide, and a pod climber!

Swing Equipment - 2 bay, single post blue swing frame with 2 black belt swing seats and 2 black bucket swing seats.

Safety Surfacing & Borders - Wood Mulch, 12" Border Timbers, ADA Half Ramp, and 2 Border Benches.

Project Timeline from Order to Install - 8 months

Full Installation in March 2023 by Noah's Park & Playgrounds.

Project Total: $28,000-$32,000