Project Details:

Structure- 5-12 Play Structure and 2-5 Play Structure, Toddler Activity Structure

Swing Equipment- Two Single Bay swing sets with 2 belt seats, 1 Single Bay swing set with 2 bucket seats, Extra Bay swing with 2 bucket seats

Independant Play Equipment- Neutron Spinner, X-Wave 2, Canyon Climber, Spring SeeSaw, Quad Hoop, Balance Beam, 2 paint stations, Musical Center including Limarimba, F.S. Bongos, Upright Piano, F.S Jamaican Steel Drums, Kettle Drums and Thunder Drums

Shading- 2-dome 40x30 shade over 5-12 play structure, (2) 1-dome 40x40 shad over 2-5 play structure and toddler play structure

Safety Surfacing and Playground Border- Fencing, Montage Plus, Gates, Artificial Turf and 6”x6” curb

Project Timeline from Order to Install- 4 months

Supervised Installation in July 2010 by Noah’s Park & Playgrounds’ CPSI and approx. 12 First Baptist Church Volunteers. Supervised installation took around 2 weeks to complete.

Project Total: $240,000 - $245,000

*Please Note: Project total price range is based on order date. Price range above has not been adjusted for yearly price increases. 

Noah's Sales/Project Representative: Shan Shepherd

 

First Baptist Church- Norman, OK