Bray City Park Playground Project

Town of Bray, Oklahoma
City Park
1013 South Brooks
Bray, Oklahoma 73055
 

Project Details:

Structures - Prague Play Structure for ages 5-12 years old in pacific blue, sky blue blue and brown. Structure complete with 2 shingled roofs, 90 degree overhead rings, overhead ladder, single wave slide, fireman’s pole, double straight slides, deep rung ladder, bongo drums, 360 degree spiral slide, gear panel and bench panel

Amenities - (2) 6’ bench with back in blue

Safety Surfacing and Playground Border - Loose rubber mulch for safety surfacing with (34) 8” border timbers for surface containment

 

Project Timeline from Order to Install- 3 months

Supervised Installation in June 2013 by Noah’s Park & Playgrounds’ CPSI and approx. 10 City of Bray Volunteers. Supervised installation took around 1 day to complete.

Project Total: $17,000 - $21,000

*Please Note: Project total price range is based on order date. Price range above has not been adjusted for yearly price increases.

Bray City Park- Bray, OK